Fort Peck Dam – Fiber OSP Project
Scope highlights:
- Designed a value engineered solution using blown-in microfiber to reduce the cost by 25% while also lowering environmental impact and enhancing safety during both the construction and ongoing operation maintenance. This VE solution also improved the mission sustainability through reduced maintenance while providing future-readiness that allows for future additions with minimal effort.
- Directional bored pathway between two buildings on-site for 24 strand fiber connection.